House of Bread Church · Foresthill

Help build the Forest Hill Retreat Center

A glass-walled lodge on the church’s forested land, permitted and ready to build — a place for the family to rest, gather, and seek God.

24 acres
In Foresthill
Permit approved
Ready to build
1,248 sq ft
One-story lodge
150+ parking
On the property

The vision

A quiet place in the trees.

House of Bread is building a small lodge so the church family has somewhere to rest, to gather, and to seek God.

The land is in Foresthill, in the Sierra foothills: pines, oaks, and a long view. The building is one story, about 52 by 24 feet, 1,248 square feet, with a main room, a kitchen, two bathrooms, and a 4-foot deck wrapped in glass.

Placer County stamped the plans “Reviewed for Code Compliance” on February 11, 2026, under permit BLD25-02885. The old house is gone. What is left is the work of building this one.

Vlad Kotyakov, Executive Pastor, is leading the project for the church. If your trade is on the list below, there is a place for you in it.

Ready to build

The paperwork is done. The hammering is not.

This is a new one-story dwelling, Type V-B, occupancy R-3, with a required fire sprinkler and wildfire construction. Codes on the sheets are the 2022 California codes. The church is inviting bids, donated labor, and donated materials. No per-trade prices are published.

Former house demolished

The soils report of May 18, 2026 says the pad is cleared.

Plans county-stamped

Placer County, “Reviewed for Code Compliance,” February 11, 2026. Permit BLD25-02885.

Engineering

Structural calculations are in the bid package, county-stamped with the plans.

Energy

Title 24 report registered with CHEERS. The design passes. Climate zone 16.

Soils

Geotechnical report dated May 18, 2026.

Fire sprinkler design

Sheet FP1, with hydraulic calculations.

Well holding tank

The existing well is expected to serve the lodge. Whether a holding tank is also needed has not been decided yet.

Temporary restrooms

Whether temporary restrooms will be on site during construction has not been decided yet.

Estimated total build cost

about $378,000

Draft estimate for the whole project. Individual trade prices are not listed.

Order of work

A simple sequence. Several of these overlap. Each name opens the trade sheet.

1
Clear the way

Trenches for water and sewer. The pad is already clear.

2
Footings

Spread footings and grade beams. The engineer watches the steel.

3
Steel

Tube columns and beams. Shop drawings first.

4
Frame and deck

Raised floor, walls, roof framing, 4-foot deck.

5
Dry the building in

Class A roof, then windows and siding.

6
Rough mechanical

Electrical, plumbing, heat pump, and the sprinklers.

7
Close the walls

Insulation, then drywall and the finishes.

8
Test and sign off

Inspections along the way. HERS at insulation and at the end.

The moment

Why your help matters now.

The plans are approved and ready to build from. Demolition is already done. What remains is the work itself — and the church family can carry a great deal of it.

The job is being run at cost

Our general contractor is running the job at cost. The remaining budget is largely labor and materials — the very things tradespeople and suppliers in the church can donate, or provide at wholesale.

Commitments now lock in savings

If the start slips by about five months, material quotes can move about 10–15%. Saying yes now — a bid at cost, donated labor, or materials at wholesale — helps keep the total closer to about $378,000.

Labor and materials are the opening

Much of what is left is work a crew can donate, or materials a supplier can give or sell at wholesale: concrete, steel expertise, a week of framing, a standing-seam metal roof, paint, cleanup, and more.

You don’t have to have a trade

End-of-job cleaning, site cleanup, and fuel or meals for the crews are real needs. They are a good fit for anyone in the church.

Five ways to help

Pick the one that fits you.

Every path opens the same form, already set to your choice. A trade sheet has the same buttons, with that trade filled in.

No trade required

No trade? You can still help.

Site cleanup and final cleaning at the end of the job are a good fit for anyone in the church. Fuel and meals for the crews help too. Tell us on the form — we’ll put you on the volunteer list.

Trades

Find your trade.

Open a card for the scope, the sheets, and a link you can text to someone.

Site, utilities & trenching

Step 1 · The pad is clear. This package is the water line, the sewer, and the ground the foundation will sit on.

OPEN

Foundation & concrete

Step 2 · Spread footings and grade beams for a 52-by-24-foot one-story lodge, plus the post footings for a 4-foot deck.

OPEN

Structural steel

Step 3 · Tube-steel columns and beams that hold the glass walls and the roof. Shop drawings go to the engineer before anything is fabricated.

OPEN

Framing & deck

Step 4 · Raised wood floor, 2×6 walls, LVL roof framing, and a 4-foot wraparound deck on a 1,248-square-foot lodge.

OPEN

Roofing & gutters

Step 5 · A Class A roof assembly, required on every new building in unincorporated Placer County, plus gutters that do not collect debris.

OPEN

Windows & doors

Step 6 · The lodge is mostly glass. Title 24 puts the glazing at about 53 percent of the wall, with a U-factor of 0.27.

OPEN

Siding, soffits & decking

Step 7 · Fiber-cement board-and-batt siding, fiber-cement soffits, and composite decking that meets the wildfire rules.

OPEN

Electrical

Step 8 · An all-electric lodge. The existing 200-amp panel stays. The new work is on sheet E1.0.

OPEN

Plumbing

Step 8 · Two bathrooms and a kitchen, tied to the existing well and the existing septic.

OPEN

HVAC

Step 8 · A central split heat pump for a 1,248-square-foot lodge in climate zone 16, with tested ducts.

OPEN

Fire sprinklers

Step 8 · The design is done. This trade installs the residential system on sheet FP1.

DESIGN DONE

Insulation

Step 9 · Climate zone 16. R-21 walls with R-4 continuous sheathing, R-60 at the ceiling, and a HERS quality-installation inspection.

OPEN

Drywall

Step 10 · Gypsum board on the walls and the ceiling, paint-ready, with the sprinkler heads and the dropped ceiling coordinated.

OPEN

Paint

Step 11 · Interior paint, plus caulking and any exposed exterior wood. Coatings have to be low-VOC.

OPEN

Flooring & tile

Step 12 · The finish floor is not specified as a product. Bid an allowance, or ask the owner what goes in the main room, the kitchen, and the two baths.

OPEN

Cabinets & counters

Step 13 · Kitchen and bathroom cabinets. There is no cabinet elevation in the set, so bid labor plus an allowance, or ask for a selection.

OPEN

Trim & fixtures

Step 14 · Interior trim, interior doors, and the finish fixtures that are not already in another trade’s bid.

OPEN

Appliances

Step 15 · All-electric appliances. A HERS-verified kitchen range hood is required. No model list is on the plans.

OPEN

Special inspections

Step 2 · A testing agency and the structural observation the permit requires, starting at the footings.

OPEN

HERS energy testing

Step 9 · A certified HERS rater. The energy report will not hold unless these tests are done.

OPEN

Plans & documents

Everything a bidder is allowed to see.

The public set: the stamped plans, engineering, energy, soils, fire sprinklers, county handouts, the window shop drawing, and the lumber list. Vendor quotes are not here.

Give financially

The ForestHill Center fund is open.

Estimated total build cost: about $378,000.

Gifts for this project go to the ForestHill Center fund on Planning Center. A general church gift can go to the main giving page instead.

Or the church’s general giving page

In-kind gifts of labor and materials can be acknowledged. For a receipt or a letter, contact the church office at (916) 344-9378 or admin@hofb.org.

Labor and materials count too. Use the form and choose “Donate labor” or “Donate or supply materials at wholesale.” The church can acknowledge an in-kind gift.

Questions

Before you drive up.

Can I walk the site?

Site walks are by appointment. The project is at 21450 Todd Valley Rd, Foresthill, CA 95631.

To schedule a walk or ask about access, contact the church office at (916) 344-9378 or admin@hofb.org, Monday–Friday, 9am–5pm.

When are bids due, and what is the schedule?

A bid due date and construction schedule have not been posted yet. Please contact the church office at (916) 344-9378 or admin@hofb.org, and we will share what is current.

What license and insurance do you require?

License and insurance requirements will be confirmed with each bidder. Please include your license number on the form, and contact the church office at (916) 344-9378 or admin@hofb.org if you need the current requirements in writing.

How are donations acknowledged?

Financial gifts to the ForestHill Center fund are receipted through Planning Center. For acknowledgment of donated labor or materials, contact the church office at (916) 344-9378 or admin@hofb.org.

Is a holding tank needed for the well?

The existing well is expected to serve the lodge. Whether a holding tank is also needed — including for the fire sprinklers — has not been decided yet. For the latest, contact the church office at (916) 344-9378 or admin@hofb.org.

Will there be temporary restrooms on site?

Temporary restrooms during construction have not been decided yet. If you can help with this, or want to know what is current, contact the church office at (916) 344-9378 or admin@hofb.org.

Respond

Tell us how you can help.

One form covers donated labor, materials at wholesale or as a gift, a bid at cost, a referral, a financial gift, site cleanup, or a question. If you opened a trade link, that trade is already checked.

House of Bread Church · (916) 344-9378 · admin@hofb.org · Mon–Fri 9am–5pm.

How do you want to help?

Trade