Bathrooms and a kitchen, tied to the existing well and the existing septic.
Scope
Rough and finish plumbing for the bathrooms and kitchen, water service from the existing well, and sewer to the existing septic.
Water heater: the floor plan notes an electric tankless unit above the cabinets. Title 24 requires a 40-gallon heat-pump water heater outside (the specified model is in the energy report, or equal). Flag this in your proposal.
Pressure test at frame (≤80 psi, A0.0 note 20). Code fixtures: 1.28 gpf toilet, 1.8 gpm faucets.
What to price
- Rough, finish, fixtures, and the water heater as you propose it — and call out which water-heater type you have bid.
- Connection to the existing well and existing septic.
Plan sheets
- A0.0 general notes
- A1.0
- A1.1
- Title 24 report (water heater)
Documents
Open or download the files for this trade, or the full bid-package folder.
Sequence
Trench with site utilities. Rough-in after framing, with the fire-sprinkler installer. Finish after drywall.
How you can help with this trade
Donate labor, donate or supply materials at wholesale, bid at cost, or refer a tradesperson or supplier you trust. Every path uses the same form, with this trade already checked.