All trades · Permit BLD25-02885
Step 9 · ENVELOPE
Insulation OPEN
Forest Hill Retreat Center · Foresthill, California
Climate zone 16. R-21 walls with R-4 continuous sheathing, R-60 at the ceiling, and a HERS quality-installation inspection.
Scope
Wall, ceiling, and roof insulation per Title 24, including Quality Insulation Installation (QII) HERS verification.
2×6 walls R-21 plus R-4 continuous sheathing. High ceiling insulation (R-60) is a required special feature. Ducts are R-8 in the attic, sealed and tested — that work lives with HVAC, but QII is this trade’s inspection.
What to price
- All insulation in the energy report, plus coordination with the HERS rater for QII.
Plan sheets
- A1.1
- Title 24 report
Documents
Open or download the files for this trade, or the full bid-package folder.
Sequence
After rough mechanical inspections, before drywall.
How you can help with this trade
Donate labor, donate or supply materials at wholesale, bid at cost, or refer a tradesperson or supplier you trust. Every path uses the same form, with this trade already checked.