Step 2 · STRUCTURE

Foundation & concrete OPEN

Forest Hill Retreat Center · Foresthill, California

Spread footings and grade beams for a 52-by-24-foot one-story lodge, plus the post footings for a 4-foot deck.

Share this trade

Scope

Excavation, forming, rebar, and concrete for the cabin foundation and the deck piers.

Spread and pad footings at the steel columns, continuous footings and grade beams, and piers for the wrap-around deck.

Soils report: allowable bearing 1,500 psf; medium-expansive clay; exterior footings at least 36 inches below grade, interior at least 18 inches; an interconnected grade-beam system.

The geotechnical engineer must observe excavations (72-hour notice).

Special inspection of reinforcing-steel placement is required (continuous).

What to price

Plan sheets

Documents

Open or download the files for this trade, or the full bid-package folder.

Sequence

After site layout. Anchor bolts and embeds must be coordinated with the steel erector.

How you can help with this trade

Donate labor, donate or supply materials at wholesale, bid at cost, or refer a tradesperson or supplier you trust. Every path uses the same form, with this trade already checked.