All trades · Permit BLD25-02885
Step 2 · STRUCTURE
Foundation & concrete OPEN
Forest Hill Retreat Center · Foresthill, California
Spread footings and grade beams for a 52-by-24-foot one-story lodge, plus the post footings for a 4-foot deck.
Scope
Excavation, forming, rebar, and concrete for the cabin foundation and the deck piers.
Spread and pad footings at the steel columns, continuous footings and grade beams, and piers for the wrap-around deck.
Soils report: allowable bearing 1,500 psf; medium-expansive clay; exterior footings at least 36 inches below grade, interior at least 18 inches; an interconnected grade-beam system.
The geotechnical engineer must observe excavations (72-hour notice).
Special inspection of reinforcing-steel placement is required (continuous).
What to price
- Confirm footing sizes against S1.0, SD1, and SN1 before you bid. A current takeoff lists column piers, continuous footings, deck piers, and foundation walls — field-verify every dimension.
- Include forming, rebar, concrete, and coordination of anchor bolts and embeds with the steel erector.
Plan sheets
- S1.0
- SD1
- SN1
- Structural calculations (grade-beam analysis)
- Soils report
- Special inspection agreement
Documents
Open or download the files for this trade, or the full bid-package folder.
Sequence
After site layout. Anchor bolts and embeds must be coordinated with the steel erector.